13 1/2 and 14th from Harrison to Washington Project

This project will occur on 13 1/2 and 14th Streets between Harrison and Washington Avenue.  It will consist of removal of existing pavement, curb, drives, storm inlets, trees, and sidewalks.  We will replace with new pavement, curb, gutter, driveways, sidewalks, tree planting, signage, pavement markings and seeding.

The project will begin May 1, 2019 through December 31, 2019.

The project amount is $186,413.  The funding source for this project will be Redevelopment Funds.