Update as of July 2023

Now- Master Planning updates & Refinement, Design Development

o

Phase 1: (River Front amphitheater, Unity Arch, Destination Playground)

August-December 2023: Phase 1 Schematic Design

January-March 2024: Phase 1 Construction Documents

April-June 2024: Phase 1 Contractor Bidding & Awarding

Late Summer 2024-Winter 2024: Phase 1 Construction

o

Phase 2: (Wabash Riverwalk, North End Gateway, Boathouse & South End Gateway)

March-May 2024: Phase 2 Schematic Design

June-August- 2024: Phase 2 Construction Documents

September- November 2024: Phase 2 Constructor Bidding & Awarding

Late winter- Summer 2025: Phase 2 Construction

o

LOCATION 

1st Street and Oak Street on the eastern bank of the Wabash River

FACTS 

  • 53 ACRES
  • Originally designed by the American landscape architect George Kessler in the early 1900s
  • Current Amenities – outdoor amphitheater, playground, dog park, multi-use athletic fields and trails, sculptural garden, and structural facilities such as the Chauncey Rose Memorial, the Paul Dresser House, the Parks Department, and the YMCA

 

PROJECT GOALS 

  • Fairbanks Park is vital public amenities of the city of Terre haute due to rich historical values and park location
  • The purpose of the Fairbanks park master plan is to create unified vision and strategic direction for the future. 6 key focus areas are identified as major components of reshaping the park –

 

  1. Wabash Riverwalk
  2. Memorial garden and amphitheater
  3. Destination Nature playscape
  4. Iconic water feature
  5. Water recreation and event venue
  6. Public art and cultural landmarks